Working hours on the construction site: Monday to Friday, 8am to noon and 1pm to 5pm.
Next major milestones
- 27 February 2026: completion of the raft slab (structural foundations).
- Until 8 April 2026: construction of the walls.
- From 8 April to 30 June 2026: installation of the beams (concrete beams that support the slab) and construction of the new square slab.
- End of June 2026: completion of the structural works.
At this stage of the construction site, the cranes as well as the concrete batching plant will be dismantled, marking the end of the main structural construction phase.