Double Deck

The Double Deck project includes the transformation of the Esplanade and the renovation of the Coupole. Located at the heart of the campus, this project will be a central element in the future of education at EPFL.

It will also bring about some changes for campus users during the four years of construction, from 2025 to 2029.

This page provides practical information and will be regularly updated during the construction period.

Latest construction news

All the construction site updates

Project highlights

Un foodtruck sur la place Cosandey de l'EPFL. Des gens font la file. Au second plan, le logo en dur de l'institution. En arrière-plan, le Rolex Learning Center - 2025 EPFL/Xurxo Adrián Entenza - CC-BY-SA 4.0

Developments

Find information about the impacts of the ongoing works for the EPFL community.

Visualisation architecturale du Double Deck: vue depuis la place Cosandey. © Atchain / Dominique Perrault Architecte, ADAGP, 2023

Visuals of the project

View pictures of the Double Deck project, at the heart of the EPFL campus.

Next steps

April 2025Relocation of the AGEPoly office
April 3, 2025Double Deck information session for the EPFL community
April 30, 2025Permanent closure of the Esplanade car park
May 19, 2025Start of preparatory construction work
July 7, 2025After the exam period, start of excavation and demolition
2025 – 2027Construction of Double Deck
2027 – 2029Renovation of the Coupole

Ask Your Questions

If you have any questions, comments, or specific needs related to your activities, please contact us at:
[email protected]